Status: Under Construction

 

About the Project

Current Work Zones

Feb. 12, 2026 Status Update

Traffic Signal Improvements

Phase 1: Installation of the crosswalk signal (pedestrian hybrid beacon or PHB) at 55th Street is nearing completion. The signal at 51st Street/Bruning Avenue is scheduled to be fully operational the week of Feb. 16, 2026.

Phase 2: Accessible Pedestrian Signal (APS) equipment is nearing completion at six intersections between I-35 and US-183.

 

Dec. 19, 2025 Status Update

55th Street to 45th Street

Phase 1: Shared-Use Path on the west side of Airport Boulevard is substantially complete. Final completion anticipated mid-January 2026.

Phase 2: The contractor will install a pedestrian signal at the intersection of Airport Boulevard and Middle Fiskville Road. The schedule for this work will be shared as soon as it is finalized.

 

Martin Luther King Jr. Boulevard to MoKan Trail Bridge

Install 10-foot-wide continuous shared-use paths on the west side of Airport Boulevard from Martin Luther King Jr. Boulevard to Springdale Road. Driveway replacement and drive walk consolidation to be implemented in areas where implementing bike and pedestrian improvements. New curb ramp installation or replacement for new sidewalk/shared-use path.